·
Continued with concrete curb & gutter,
sidewalk, and driveway apron replacements that were damaged during construction
or in poor condition.
·
Made repair to water main connection near north
end of project site due to unforeseen circumstance.
·
Adjust manholes within curb & gutter to
final grade to allow for new concrete curb & gutter to be installed.
Work Anticipated to be completed Next week, June 27th
to July 1st
·
Complete concrete curb & gutter, sidewalk,
and driveway apron replacements that were damaged during construction or in
poor condition.
·
Remove existing pavement in preparation for new
asphalt pavement
·
Perform repairs to existing materials to provide
suitable material under pavement as needed
·
Grade existing materials in preparation for new
asphalt pavement
·
Install first layer of asphalt pavement
The contractor was unable to complete the concrete
replacements as anticipated last week. The contractor is planning to complete
the remaining the concrete curb & gutter, sidewalk, and driveway apron
replacements early next week. If the concrete curb & gutter or sidewalk in
front of your driveway or concrete driveway apron is being replaced, access to
your driveway will be restricted for 4-5 days. Residents affected by driveway
restrictions will be notified prior to removing, framing, and pouring the driveway
to give you ample time to remove any vehicles from your driveway or garage.
The project is moving into a new phase next week, roadway
rehabilitation. The contractor will remove the existing pavement, perform
needed repairs, and grade the existing materials as needed in preparation for
the new asphalt pavement. If all goes as planned, the first layer of asphalt
pavement will be installed next week, prior to the July 4th Holiday.
The installation of the first layer of asphalt pavement is a major project milestone. Once this layer of pavement is installed, the amount of dust is greatly reduced and a smooth driving surface will be provided.
Following the paving of the first layer of asphalt pavement,
the contractor will begin landscape restorations, final testing and inspection
of the underground utilities, adjusting manholes, and other miscellaneous tasks
prior to installing the final asphalt surface layer.
Thank you again for all your patience and understanding have
you have been dealing with the dust and uneven roadway for the past few months.
If all goes as planned, the first layer of asphalt pavement will be installed
prior to the weekend and provide relief for both of these inconveniences.