·
Rough grading of areas disturbed by construction
activities
·
Final testing of underground utilities
·
Internal televising of underground sewers
·
Adjusting structures to final grade
·
Walk-through with Village staff to find any
items that need additional work
·
Made minor repairs at locations identified by
Village staff
Work Anticipated to be completed Next week, July 18th to July 25th
·
Complete grading of areas disturbed by
construction
·
Installation and grading of topsoil
·
Asphalt surface paving
The contractor has completed
the final testing and work associated with the underground utility portions of
the project. The contractor has started some minor grading of the areas
disturbed during construction. The contractor will continue to perform grading
of disturbed areas as well as installation and final grading of topsoil. The
timing of the sod installation is still being determined. Due to the hot and
dry weather the past few weeks, this is not the optimum time to install sod.
Should the sod installation be delayed to a time with more favorable growing
conditions, we will let you know when the sod installation is scheduled to
occur.
Paving of the asphalt surface
layer is scheduled for next week. Additional information will be provided when
the schedule is finalized regarding travel cautions and restrictions during the
paving operations and prior when the existing asphalt will have a thin layer of
oil sprayed on it.
Thanks again for all your
patience, understanding, and cooperation during the construction project.