Monday, May 2, 2016

Construction to Start Week of May 2nd

Welcome to the Executive Lane Improvements Construction Blog!

Updates will usually be posted on Friday's of each week. Typical posts included work completed the previous week, work anticipated to be completed the upcoming week, and other pertinent information.

Mailed or hand-delivered letters and door hangers will also be utilized to provide additional and time sensitive information. These notices are used to notify residents of scheduled water shut-downs, driveway and/or roadway closures, transition between construction phases, and other instances as it is required.  Please be on the look-out for these notices.

Later this week the contractor will begin mobilizing equipment and materials, grinding-in-place the existing asphalt pavement where the new water main will be installed, and potentially beginning the water main installation.

The week of May 9th, the construction is anticipated to be in full-swing with the installation of water main piping along Executive Lane.

The Village understands the inconveniences that are associated with living within a construction area. Please understand everything possible will be done to minimize any delays or inconveniences you are likely to experience. Thank you in advance for your patience and understanding.

Please feel free to contact the Village Project Manager, Tim Schwister, with any questions or concerns. Tim's contact information is listed on the right side of the Blog Page.

There will also be an on-site project representative available throughout the project that can help answer questions or provide assistance as needed.