Work Completed Last Week, May 9th to 13th

·         Installation of 12-inch PVC water main along Executive Lane from Executive Court to Executive Circle

Work Anticipated to be completed Next week, May 16th to 20th  
·         Continue with new 12-inch water main installation along Executive Lane working north from Executive Circle to end of the project limits near Imperial Drive / access road to pumping station.
·         Begin new 8-inch water main installation along Executive Court
·         Begin new 8-inch water main installation along Executive Circle
·         Begin storm sewer replacements

The contractor will continue to install new water main and begin storm sewer replacements along the project site next week.