Started performing the required testing prior to placing the newly
installed water main into service and water service replacements
·
Storm sewer replacements as required
·
Sanitary sewer replacements as required
Work Anticipated to be completed Next week, May 30th
to June 3rd
·
Receive required approvals to place new water main into service
·
Begin water service replacements along Executive Court
·
Complete storm sewer replacements as required.
·
Complete sanitary sewer service replacements as required
No work will be performed on-site over the holiday weekend
Have a safe and fun Memorial Day!!!