Friday, June 3, 2016

Water Service Replacement to Begin This Week

Work Completed Last Week, May 30th to June 3rd  
·         Continued performing the required testing prior to placing the newly installed water main into service and water service replacements
·         Grind-in-place of the remainder of the existing pavement along the project limits

Work Anticipated to be completed Next week, June 6th to June 10th  
·         Receive required approvals prior to placing water main into service
·         Begin water service replacements along the project site

Water service replacements will begin this week along the project site. Water services will be replaced from the new water main to the existing valve and box located in front of each home. During the water service replacement, water to individual homes will be shut-off for approximately 1-2 hours while the transition from the old service to the new service is made. The contractor will notify each resident individually regarding the approximate time and day of the water shut-off prior to turning off the water.

It was determined the best option was to grind the remainder of the existing roadway in-place prior to starting the water service replacements. During water service replacement, the contractor will be excavating across the entire width of the roadway. This will make travelling along Executive Lane increasingly more difficult throughout the coming weeks. You may be asked to take an alternative route depending on the location the contractor is working.  Should a cul-de-sac area need to be closed to facilitate construction, residents within those areas will be given prior notice.

Thank you again for all your patience and understanding as the next phase of construction begins, water service replacement. It is anticipated it will take approximately 2 weeks to complete all the water service replacements.